Guidance figures should be given, although it would be the responsibility of the Contractor to ensure they calculate the total materials required to complete the work and achieve the standards.

Item Estimated Quantity Contractor's Proposed Quantity
Fencing / safety cordon around the perimeter of works 1  
Stone for Sub-base: {720m² x 100mm depth}
(Estimated consolidated mass of 1.6 t/m³ )
115 Tonnes  
Sandy loam for Square: {720m² x 150mm depth}
(Estimated consolidated mass of 1.75 t/m³ )
189 Tonnes  
Sandy loam for Outfield { ~5,000m²} 200 Tonnes  
Clay loam : {720m² x 120mm depth}
(Estimated consolidated mass of 1.75 t/m³ )
151 Tonnes  
Pre-seeding fertiliser : say to the whole of the square and 25% of the outfield = 720 + 1250 m² = ~ 2000m² @ 50 g/m² 100 kg  
Grass seed : say to the whole of the square and outfield = 5720m² @ 34 g/m² 200 kg  
Maintenance materials As required to achieve the standards e.g. grass seed, fertiliser, top-dressing, pesticides, etc.
The contractor will be expected to give a breakdown of the anticipated amounts.
 

Note: An indication would need to be given as to how much, if any, of the excavated material might be able to be used within the construction works.